Expert Verified ENA G99 Standard Updated 2026

G99 Inverter Calculator

Calculate total inverter capacity and effective export limits to determine your UK DNO connection route under Engineering Recommendation G99.

⚡ Free Tool No Signup Instant Results
SOLAR PV INV 1 INV 2 INVERTERS X EXPORT LIMIT DNO GRID ENA G99 CONNECTION SCHEME
G98 Limit | 3.68 kW per phase
Grid Standard | ENA G99
Technology | Solar & Storage
Connection | G98 vs G99 Check

G99 Inverter Calculator

Qty
kW

How to Use G99 Inverter Calculator

Verifying grid eligibility routes is mandatory in the UK for clean energy assets. Our calculator handles individual ratings, multiple units, and export limit schemes to check whether you qualify for G98 micro-generator terms or need a formal DNO application. Follow these practical steps:

  • 1
    Select supply type. Choose Single Phase (typical for domestic properties) or Three Phase (typical for larger commercial developments and agricultural connections).
  • 2
    Enter inverter quantity. Input the number of independent grid-tied inverters in the system (e.g. 2 inverters for solar and battery storage systems).
  • 3
    Enter individual rating. Input the continuous maximum active AC power rating (in kW) for a single inverter.
  • 4
    Choose export limitation. Indicate if you are using an ENA-approved export limiting scheme (G100 standard) to cap the export current.
  • 5
    Enter export limit value. If using limitation, input the programmed threshold in kW (for example, a standard 3.68 kW single-phase limit).
  • 6
    Click Calculate. Review your G98/G99 compliance outcome, connection pathway, and the specific application form required.

How to Calculate G99 Inverter Capacity

Under Engineering Recommendation G99, DNOs regulate the active generation power entering the network. The capacity limits are calculated based on the maximum export capability of the entire system. Below are the equations used to size your connection capacity.

G99 Mathematical Formulas

To determine the installed capacity, effective export capacity, and per-phase current values, the following math is applied:

Total Installed Capacity (kW):

Total Capacity = Number of Inverters × Inverter Rating

Effective Export Capacity (kW):

Effective Export Capacity = Lower of: Total Capacity OR Export Limit

Three-Phase Capacity Per Phase (kW):

Capacity Per Phase = Effective Export Capacity ÷ 3

Worked Example: Single Phase Solar PV System

Consider a standard residential system with multiple generators where export limitation is not implemented:

  • Supply configuration: Single Phase
  • Number of Inverters: 2
  • Inverter AC Rating: 3.00 kW each
  • Export Limitation: No

Step-by-step capacity evaluation:

Total Capacity = 2 × 3.00 kW = 6.00 kW
Effective Export Capacity = 6.00 kW

Result: Since the Effective Export Capacity is 6.00 kW, which is greater than the standard G98 threshold of 3.68 kW (6.00 kW > 3.68 kW), a G99 Prior Approval Application is Required before the system is connected to the grid.

In the UK, DNO approval is necessary to ensure local grid assets (transformers, cabling, voltage regulation equipment) can tolerate the extra power without causing voltage spikes or system failures.

G99 Inverter Capacity Chart

This reference chart details ENA connection pathways, application requirements, and standard system routes across single and three-phase supplies. Values assume a standard nominal phase-to-neutral voltage of 230 V (400 V line-to-line) and unity power factor.

System Type Export Capacity Typical Connection Route Application Requirement Example System
Single Phase Up to 3.68 kW G98 Notification 3.68 kW Solar PV
Single Phase Above 3.68 kW G99 Prior Approval 5 kW Solar PV
Three Phase Up to 11.04 kW Total Typically within 3.68 kW per phase Assessment Required Commercial Solar
Three Phase Above 11.04 kW G99 Prior Approval Large Solar Installation
Three Phase 50 kW+ Enhanced Assessment DNO Review Commercial Generation

Note: Actual approval requirements depend on DNO assessment, export limitation arrangements, and site-specific network constraints.

G99 Inverter Frequently Asked Questions

Engineering Recommendation G99 (EREC G99) is the UK grid connection standard issued by the Energy Networks Association (ENA) for connecting generation equipment (like solar PV and battery storage) to the distribution network. It replaced G59 in 2019 and applies to systems exceeding 16 Amperes per phase.

Any inverter system in the UK that has a continuous AC output capacity exceeding 16 Amperes per phase (which corresponds to 3.68 kW on a single-phase 230V supply, or 11.04 kW on a three-phase 400V supply) falls under G99 requirements and requires prior approval.

The G98 limit is 16 A per phase. Under ENA G98, generators of 16A or less per phase can be connected using a simplified "notify after installation" route within 28 days of commissioning. Exceeding this limit requires a G99 application.

Yes, an ENA-approved export limitation scheme can cap export capacity at G98 limits (e.g., 3.68 kW). However, because the physical inverter rating is larger, you must still submit a G99 application (often Fast Track Form A1-1) to the DNO before installing the system.

G99 capacity is calculated as the sum of all grid-connected inverter AC output ratings. If export limitation is applied, the effective export capacity is the lower of the total inverter capacity and the export limitation value set on the G100-compliant limiter.

Yes, battery energy storage systems (BESS) are treated as generators under ENA rules. If the combined rating of the battery inverter and the solar PV inverter exceeds 16A per phase, a G99 application is required even if the battery is programmed for self-consumption.

A standard G99 application (Type A or B) typically takes between 45 to 65 working days for the DNO to assess and approve, depending on grid constraints. G99 Fast Track applications (Form A1-1) are processed faster, typically within 10 to 20 working days.

Yes, compliance with EREC G99 is legally mandatory under the UK Distribution Code for all generating units connected to the distribution network that do not qualify under the G98 notification scheme. Connecting without approval is a breach of grid terms.

Explore More Solar & Grid Calculators

🔗

Solar Inverter Calculator

Determine optimal sizing matching inverter specs to solar panel arrays.

Calculate Inverters →
🔌

Solar PV System Size Calculator

Calculate total solar panel count, peak output, and required physical roof area.

Size Solar Array →
📉

Battery Storage Calculator

Size battery backup storage capacity and runtime based on electrical loads.

Size Battery Backup →
🔋

Solar Panel Output Calculator

Estimate solar generation output per day and month based on geographic location.

Calculate Panel Output →